Preparation checklist: make separate measurable schedules

What and how to measure before opening a calculator

Measure each baluster run between the inside faces of its posts, in one unit, and retain every run separately. Measure the selected baluster's supplied width and enter a project-supplied maximum clear gap. A post ends one run and starts another, so its two end gaps must not be pooled into a longer imaginary opening. Use the Baluster Spacing Calculator to solve those independent clear runs for the smallest whole baluster count and equal end/intermediate gaps.

For a lumber line, copy the supplier's nominal thickness, nominal width, nominal length and supplied piece count. Record actual physical dimensions separately only when you need the solid-volume check; they do not replace nominal dimensions in a board-foot tally. Use the Board Foot & Lumber Cost Calculator to keep nominal board feet, actual volume, an entered allowance and one local price basis visible.

The other deck worksheets remain inputs with different meanings: the Decking Calculator estimates board coverage/order, the Post Hole Concrete Calculator estimates entered hole geometry, the Fence & Deck Stain Calculator estimates finish coverage, and the Deck Building Cost Calculator keeps supplied quantities and quote scopes in a budget. None transfers quantities automatically, selects the same product system, or designs structure. For a related structural planning boundary, see the live Stair Building Basics guide.

C19 worked calculation: one clear run, equal gaps and a baluster order

Illustrative C19/UAT inputs only: one 2.00 m clear run, 0.050 m baluster width and a 0.100 m maximum target gap. These reproduce the independent fixture and are not a product or code recommendation. The calculator uses n = ceil((L − M) ÷ (w + M)), then g = (L − n × w) ÷ (n + 1).

Synthetic C19 clear-run worksheet
StageCalculationResult
Balustersceil((2.00 m − 0.100 m) ÷ (0.050 m + 0.100 m))13 balusters
Equal gaps13 balusters + 1 end/intermediate gap14 gaps
Equal clear gap(2.00 m − 13 × 0.050 m) ÷ 140.096428571 m = 96.43 mm

The order from this single run is 13 balusters. Repeat the calculation for every post-bounded opening and add the resulting whole counts. Do not divide a combined perimeter by a spacing target: it hides end gaps, posts and openings. Posts, rails, connectors, fasteners, cuts, spares and labour are separate purchase lines unless a selected system's documented schedule says otherwise.

C20 worked calculation: nominal board feet, actual volume and price basis

Illustrative C20/UAT inputs only: five supplied boards with nominal purchase dimensions 2 in × 6 in × 10 ft, actual physical dimensions 1.5 in × 5.5 in × 10 ft, 0% allowance, and an illustrative local rate of USD 3.00 per board foot. These values explain the worksheet; they are not a lumber-size, allowance or price recommendation.

Synthetic C20 lumber worksheet
StageCalculationResult
Nominal board feet per piece2 in × 6 in × 10 ft ÷ 1210 bf/piece
Net and ordered board feet5 pieces × 10 bf/piece × (1 + 0 ÷ 100)50 bf
Actual solid volume check5 × 1.5 in × 5.5 in × 10 ft4,950 in³ = 0.081116 m³
Illustrative extension50 ordered bf × USD 3.00/bfUSD 150.00

The independent decimal-rate C20 fixture uses an illustrative USD 3.005/bf instead: 50 bf × USD 3.005/bf = USD 150.25 after final-line currency rounding. That is a pricing-precision check, while the UAT's USD 3.00/bf example above expects USD 150.00. A board foot is a nominal purchasing tally; 50 bf is not a claim that the boards occupy 50 cubic feet or that their actual volume is 0.081116 m³. Conversely, the actual-volume check does not change a supplier's board-foot price basis. If the supplier quotes per piece, price the five supplied pieces at that basis instead; do not apply both per-piece and per-board-foot prices. The calculator's allowance expands ordered board feet but deliberately does not invent extra whole boards, stock lengths or bundle quantities.

Changed-input comparison: a smaller target gap changes the baluster order

Keep the C19 clear run and baluster width above, but change only the maximum target gap from 0.100 m to 0.090 m. The new count is ceil((2.00 m − 0.090 m) ÷ (0.050 m + 0.090 m)) = 14 balusters. That makes 15 equal gaps; each is (2.00 m − 14 × 0.050 m) ÷ 15 = 0.086666667 m = 86.67 mm. This matches the C19 UAT changed-input result. The one tighter input adds one baluster and one gap; it says nothing about the required post, rail, structural or fastener design.

Common ordering mistakes and practical purchase or estimate checklist

Clear railing opening and separate lumber scheduleA post-to-post clear railing opening on the left feeds a baluster quantity. A separate supplied lumber schedule on the right feeds nominal board feet, actual solid volume, and a price basis. Neither diagram sizes structure.One clear post-to-post runmeasure only between inside post facessolve each opening for equal gaps; add countsSupplied lumber schedulenominal 2 in × 6 in × 10 ft5 supplied piecesboard-foot tally ≠ actual solid volumekeep supplier stock, price basis and structural review separatePlanning diagram only: verify the selected system, drawings, supplier schedule and responsible structural/compliance requirements.
The railing opening and lumber line answer different questions. Do not use a baluster count to infer posts or rails, or use board feet to select their structural size.

Sources, scope, and limitations

Deckorators' Classic Baluster installation instructions (accessed 14 October 2026) are primary product instructions to check for a compatible selected railing system. They do not create a universal clear gap, post spacing, fastening pattern, load design or compliance result for the illustrative values below.

US Forest Service board-foot information (accessed 14 October 2026) supports treating a board foot as a conventional lumber tally. It does not select nominal or actual dimensions, grade, species, treatment, stock length, price, waste or structural use.

Scope limit: the synthetic values below reproduce the C19/C20 calculator and UAT checks; they are not spacing, lumber, cost, fastening or structural recommendations. Current selected-system instructions, local requirements, drawings, supplier confirmation and the responsible designer/installer control the work.