Specified Footing & Formwork Quantity Takeoff

Measure specified footing concrete and selected formwork edges, then keep net, ordered, and stock-board quantities distinct.

Page revision:

Preparation checklist

Start with the drawing revision, detail callouts, and the supplier's current ordering terms. A quantity takeoff is strongest when it preserves what the documents say instead of converting a vague sketch into an invented footing or form design.

What to measure and how to record it

For a rectangular strip or pad, record length × width × depth in one unit system. Its volume is L × W × D. For a cylindrical pad, record diameter and depth: volume is π × diameter² ÷ 4 × depth. Add only sections that are different physical concrete; then subtract a known shared-junction volume once. The Concrete Footing Quantity Calculator keeps those section, overlap, allowance, supplier-increment, and optional-price stages separate.

For formwork, record each selected edge as its own run: formed length, formed height, number of board courses, and stock-board length. Contact area is formed length × height. Board pieces per course are ceil(run length ÷ stock length), then multiplied by courses. The Concrete Formwork Calculator rounds each entered run independently by default, so a remainder from one edge is not silently used on another.

For broader concrete-shape and supplier-yield context, see the live Concrete Shapes and Screed Bag Yields guide. It covers different quantities; it does not replace this selected-edge formwork takeoff.

Worked footing quantity (C11, illustrative)

This synthetic example uses one specified strip and four separate rectangular pads. It deliberately makes no recommendation about whether these dimensions are suitable.

  1. Strip: 10 m × 0.4 m × 0.2 m = 0.800 m³.
  2. Four pads: 4 × (0.6 m × 0.6 m × 0.25 m) = 4 × 0.090 m³ = 0.360 m³.
  3. Net concrete: 0.800 m³ + 0.360 m³ − 0.000 m³ entered overlap = 1.160 m³.
  4. Order quantity with no allowance: 1.160 m³ × (1 + 0%) = 1.160 m³.
  5. Illustrative supplier increment: ceil(1.160 m³ ÷ 0.25 m³) = 5 increments, so 1.250 m³ purchased. The 0.25 m³ increment is an example input, not a supplier recommendation.

Notice the three useful records: 1.160 m³ net geometry, 1.160 m³ allowance-adjusted order basis, and 1.250 m³ purchased after the hypothetical increment. Do not price a rounded supplier quantity as if it were the installed geometry.

Worked formwork quantity (C13, illustrative)

For a 5 m × 4 m rectangle, assume all four edges are explicitly selected as formed, each is 0.2 m high, one board course is used, and stock boards are 3 m long. These are fixture values, not formwork instructions.

  1. Formed length: 5 m + 4 m + 5 m + 4 m = 18 m.
  2. Contact area: (5 m × 0.2 m) + (4 m × 0.2 m) + (5 m × 0.2 m) + (4 m × 0.2 m) = 3.6 m².
  3. Boards on each run: ceil(5 m ÷ 3 m) = 2; ceil(4 m ÷ 3 m) = 2. With one course, the four runs need 2 + 2 + 2 + 2 = 8 boards.
  4. Purchased board length: 8 boards × 3 m = 24 m of stock length.

Contact area describes the selected face area; it is not a board count. Board count follows the stated stock length and independent-run rounding. Stakes should be a separately supplied manual count or a project-selected spacing/end convention, never inferred from this illustrative layout.

Changed-input comparison

Change only one input at a time to see which quantity moves. In the footing example, applying a 10% order allowance changes the ordered quantity to 1.160 m³ × 1.10 = 1.276 m³; the net geometry remains 1.160 m³. With the same illustrative 0.25 m³ supplier increment, ceil(1.276 ÷ 0.25) = 6 increments, or 1.500 m³ purchased.

In the formwork example, instead mark one 5 m edge unformed. The selected formed length becomes 18 m − 5 m = 13 m; contact area becomes 3.6 m² − (5 m × 0.2 m) = 2.6 m²; and the independently rounded board count becomes 6 boards. That is a scope change, not a reason to assume the excluded edge needs no support or preparation.

Common ordering mistakes

Practical purchase or estimate checklist

Specified footing sections and selected formwork edges are separate takeoffsAt left, a ten metre strip and four separate rectangular pads are measured by their specified length, width and depth. A shared intersection is labelled as an entered overlap only when it is the same physical concrete. At right, a five by four metre rectangle has three selected formed edges, one unformed edge, and independent stock-board cuts along each selected edge.Concrete geometry: specified sectionsstrip: length × width × depthpads are separate L × W × depth sectionssubtract a junction only when entries overlap physicallyFormwork: selected edges onlydashed edge: unformed, exclude itround board pieces independently for each formed run
Measurement diagram only. Blue edges are the edges deliberately included in a formwork takeoff; they do not prescribe where forms, stakes, or structural reinforcement are required.

Sources, scope, and limitations

NRMCA CIP 31 — Ordering Ready Mixed Concrete is official industry ordering context: confirm the actual mix, delivery conditions, minimums and increment with the local supplier. It does not select a footing size, allowance, or purchase quantity for this guide's example.

Doka formwork sheets user information is product-specific context for formwork products. It is not a universal board length, course height, stake spacing, reuse policy, capacity, or formwork-design rule. Use the selected system's current documentation and the project's specified edge scope.

All numbers below are synthetic, unit-labelled calculation examples taken from the independent C11 and C13 fixtures. They illustrate arithmetic only. This guide does not determine footing dimensions, bearing, concrete mix, reinforcement, formwork design, stake spacing, safety, code compliance, excavation, or placement method.